Track Sectioning Site (TSS) Cabinets

As part of the Great Western Electrification Project, UKPNS were contracted by Network Rail via a Framework to deliver the Electrification Distribution requirements.

Part of the scope of this work included a large number of Remotely Operated Motorised OLE Switches. As this was a relatively new concept on the Railway, no standard solution existed to provide LV Power and Control to the Switches.

UKPNS therefore contacted ICS because of their In-House Engineering expertise and ability to respond to Client queries quickly. After initial discussions regarding developing a conceptual design, UKPNS awarded ICS the Contract to develop, design and manufacture a solution.

ClientUKPNSShare

Equipment & Services

  • Streamline Design approach introduced to produce a ‘Single Common Design’ suitable for Operation of up to 8 Switches
  • ICS Solution of a Stainless Steel Cabinet containing an Isolation Transformer, AC Distribution for the Switch Heaters, DC Battery
  • Charging Unit for 48V DC Motor Supplies & Power Supply for the RTU Control Units
  • Successful manufacture and delivery of a total of 112 Cabinets for the planned sites between Reading and Bristol

Key Facts

  • Provision of In-House Engineering Expertise to develop a single common design
  • Full Collaboration & Communication with UK Power Networks as the Client
  • Demonstration of ICS’s In-House Engineering Capability and our willingness to quickly respond to End Customer requirements
  • Successful manufacture and delivery of Trackside Infrastructure