H2 Enabling Works: Euston Package

As part of the HS2 Enabling Works the disused Carriage Shed on the approach to Euston Station was due to be demolished.

The scope: the Building at Euston housed the 11kV Ring Main Feed from the Substation at Camden through to the Substations within Euston Station, including the Cables which ran along the wall at High-level. ICS were employed by Skanska for the Supply of a Replacement 11kV Package Substation complete with 11000/415V Transformer and LV Distribution Feeder Pillar to provide the required LV Supplies to the EMU Stabling Point Staff Building and Light Towers.

ClientSkanskaShare

Equipment & Services

  • Design and Supply of a replacement 11kV Package Substation, including 11000/415V Transformer and LV Distribution Pillar
  • Undertaking of Site Surveys of the HV Cable Routes and Main Substations to investigate and provide all relative data to assist with future work planning. This was associated with the entire Euston area 11kV Distribution Network
  • Fully Tested & Proved System Offsite, prior to delivery
  • Offload, Delivery and Installation within Central London

Key Facts

  • Provision of Expertise within a ‘Constrained Location’ in Central London

  • Full Collaboration & Communication with Skanska as the Client

  • Diligent Safety Management with NO Accidents or Incidents

  • ICS’s ability to provide HV/LV Solutions for bespoke Network Rail Plant requirements, including Depot & Shore Supplies and Tower Lights